W.S. Scott Auditorium Renovation


Renovation work on W.S. Scott Auditorium remains on schedule. Exterior block has been set, and some interior block work remains. Electrical work continues, while most of the mechanical below the roof is complete. Roof joists and roof decking have been installed.

Upcoming work includes exterior brick, mechanical systems on the roof, and work on the elevator. Among the improvements are expanded restrooms for women and men, a new concession stand and ticket booth, Tiger Athletic Hall of Fame Room, offices, and an elevator that will take people to the top area inside the auditorium. The project is expected to be completed by the end of August.

 

Summer 2004