Construction on new dorm moving right along

 

Dorm ConstructionConstruction on Cowley College's 96-bed dormitory is expected to be completed prior to the 2008-09 school year.

All of the precast panels for the first and second floors are in place, and the third floor is in process. Hollowcore flooring has been installed between floors one and two and floors two and three. Much of the interior block work is completed on the first floor, with stair assemblies in place from the first to second floor.

The timeline will have the crane off site by the end of the month and have the roof going on the building in early April, with interior drywall and painting beginning in mid April, and brick veneer in early May.